THE DIFFICULTIES ENCOUNTERED IN THE WORKS OF THE HURNAI
RAILWAY—ITS CONSTRUCTION—THE OPENING CEREMONY.
WE may now proceed with the more important particulars of the
work, of which we have just given a general sketch: first touching again on
that section of that great oval route which was constructed on the narrow
gauge and was under Colonel Lindsay’s charge.
Colonel Lindsay’s Bolan Railway was undertaken at a time when
the political outlook rendered it necessary to mobilise (a portion of the
Indian army. The project was prepared by Colonel Lindsay, R.E., for laying
down the rails on the surface of the Bolan Pass, which practically is the
bed of the Bolan River, dry for the greater part of the year, but liable to
floods. Colonel Lindsay was compelled to surrender charge of the work on
account of an accident, and was succeeded by Mr. O’Callaghan, C.I.E., by
whom it was carried to its completion under great difficulties, owing to the
unhealthy season of 1885. The line runs for the first forty miles with a
fairly good gradient, and, although liable to be flooded in the lower part
of the Pass, is in ordinary seasons an excellent working railway. The steep
gradient in the higher part of the Pass prohibits the construction of a
broad gauge line, and the last part is on the metre gauge up a very steep
incline. From the top of the Pass, about 6,000 feet, it runs in the level up
to Quetta. It is now proposed to substitute for this narrow gauge portion a
broad gauge line on another system, a development of that with which
visitors to the Righi are familiar, and when this latter is carried out
there will be two lines of broad gauge from India to Beloochistan.
To turn now to Colonel Browne’s line. He had joined at Sibi
to start the arrangements and work in October, 1883. He had, as above
stated, arranged to organise the collection of labour, material, and
supplies, and to begin the work itself in the lowest of the sections—Sibi to
Nari; to concentrate the labour in the warmer sections and localities in the
winter, and to change thence to the higher and cooler spots in the summer.
This answered perfectly, except in respect of outbreaks of cholera, which
seemed to be affected less by climate than by the large gatherings at
various spots from time to time of troops and followers and Commissariat,
with their attendants, supplies, and transport for the frontier posts at and
about Quetta.
We have noted that in consequence of departmental changes
Browne found himself at once hampered by intolerable checks, interferences,
and prohibitions. The initial auxiliary works, always customary as conducive
to economy both of time and money, such as tram lines, rolling stock, etc.,
were prohibited, leading at once to an enormous loss, owing to the
consequent unavoidable substitution of camel carriage. Even the acquisition
and use of the juniper forests, which provided the only wood that grew in
those parts, were disallowed, however judicious the arrangement, and however
acceptable to the people. In every sort of point, in fact, which should be
left to the chief Engineer and in which he should have a free hand, he was
dealt with as if only an executive—nay, as if only an assistant—Engineer,
and was kept under inquisition and restrained by orders from an unskilled
and unqualified control, with the natural results of delay and expense and
confusion. There was even much time lost, from the same cause, before he was
supplied with instruments or survey appliances, though this surveying
(preparatory to designing and estimating the operation) was obviously as
essential work as any that there could be, at the start.
After, however, Browne had joined his work and found that his
masters were changed, and that he was likely to have to think more of his
estimates, he suited his arrangements and work to the state of the case, and
sent in the customary “preliminary sketch estimates ” without any avoidable
delay. But, at the same time, he stated and showed first that, without any
doubt whatever, these were of no value at all; and next that no estimates
could, by any possibility, be prepared that would at all be a useful guide
to the eventual cost until close on completion.
At the outset, however, the interference described did not
last for more than the first three months. In that time, owing to Browne’s
energy, good communication was made up to the first point of serious
difficulty; and in six months—i.e. by the end of March, 1884, when the
weather began to get hot—three tunnels were in full progress, the
foundations of numerous bridges had been securely laid, contracts for work
and machinery had been entered into, and enormous quantities of rock work
had been carried out. But, as will be seen, the interference was afterwards
resumed, and with greater virulence.
It has been shown that the arrangements and understanding
which were agreed to by the Government before Browne left Simla to start the
work of the line included this provision—that he was to push on the line as
rapidly as possible without waiting for the estimates. It had all been fully
discussed, and there was no sort of doubt about the meaning of the
instruction or understanding. There was not to be any omission or neglect of
estimating—and, in fact, there were estimates framed from the very
beginning, but undeniably these were quite useless—and, under the political
exigencies of the case, speed in the construction of the line was the
primary and essential necessity, estimates and similar matters of ordinary
departmental routine being left to be carried out as speedily as the
circumstances of such an exceptional case might admit. These instructions
were frequently repeated to him from high quarters, from time to time, as
a bona fide, though not official matter.
There was difficulty again raised later on about this
preparation of estimates; for the whole nature of the work, and of the route
even, when once finally known, with its miles of tunnels, made it quite
certain that it must be impossible to foresee at any time what the details
of the works with their invisible sites must be, or to prepare, until close
on completion, estimates that could serve any useful purpose, or give a clue
to the eventual cost. This subject is dealt with later on separately, in
order to prevent its interfering with the general narrative of the work.
With these remarks we quit here the subject of the estimates.
To turn to the work itself, the Hurnai line was one that
involved many classes of engineering difficulties, which have been already
indicated, and may be summed up as follows:
The known difficulties lay in the inaccessibility of the
sites both generally and in detail; the gravity and variety of the engineer
work involved, and the impossibility of examining and realising its details
beforehand; the barren, mountainous, and desert character of the route of
the line; the wild and warlike character of the sparse population that
occupied it; the necessity for importing everything, whether in the shape of
supplies, of labour, or of material and machinery; the narrowness and depth
of the defiles; the force and fluctuations of the rivers and torrents that
traversed them; the want of space; the excessive graduations of height; and
lastly, the great variations of temperature, which severely affected the
workpeople.
Besides these there were the unknown difficulties that
eventually developed and are dealt with at greater length farther on;
arising from the excessive rainfall and the consequent floods sweeping away
the works and plant time after time, especially in the earlier stages; and
then the outbreaks of sickness, such as virulent and continuous cholera,
fever, and scurvy. These epidemics were brought about, it is supposed, or at
any rate increased, by the great gatherings of Commissariat cattle and of
troops and their followers, in the roads and grounds in the near
neighbourhood, at and en route to Quetta, in expectation of war.
But engineering difficulties were not the only ones
encountered in this great undertaking. On a line which runs from nearly one
of the hottest parts in India, only a little above the level of the sea, to
a height some thousands of feet greater than that of any railway in the
world, great extremes of heat and cold were unavoidably experienced. The
thermometer has been known to register in the Nari Valley as much as 1180 Fahr.
in the house, while on the higher part of the work it has been as low as
180 below zero in the verandah during the winter. The cold was so great as
to prevent the laying of the permanent way, rails snapping from the frost.
Political and military difficulties were also expected, but
they did not arise, or at any rate prove serious; which was probably due, in
a measure at least, to Browne’s special and mysterious influence with the
natives, and especially the Ghilzyes.
To these must be further added those very serious
difficulties that were from time to time occasioned by climatic and special
causes.
In August and September, 1884, the last months of the first
year of work—a very early stage of the enterprise—came, alas! the first
great check to progress—in the appearance of a regular plague of sickness,
fever, and scurvy (but not cholera) among the workpeople and the staff, of
whom large numbers died, while the rest were so prostrated as to be fit for
very little work. Sixty per cent., for instance, of the Sappers were in the
hospital.
Then in November, the beginning of the second year of work,
matters grew from bad to worse, and severe cholera appeared; labour was
greatly weakened, and all the Afghans deserted! This cholera reappeared in
the following May (1885) and spread severely, Captain Ewen Cameron, R.E., a
very valuable officer on the Bolan Road, falling a victim to it. On the
Hurnai itself Mr. Sullivan, the bridging contractor, Mr. Phillips, a New
York engineer in charge of the tunnelling apparatus, and the platelaying
contractor, Mr. Barnes—all these valuable engineers of the line and many
others died and were lost to the work. This great sickness continued in
June, in which month fourteen out of twenty-four officers were crushed with
fever; while some whole classes of employees, such as the telegraph and post
office clerks, fled in a body, and work was stopped for the time. After a
while these exceptionally serious epidemics ceased; the milder customary
illnesses, however, continuing as a matter of course.
But in this same year, 1885, the second year of excessive
sickness, there appeared another great and unexpected cause of loss, delay,
and trouble, in the occurrence of floods of unheard-of force. They began
early in the year, and were due to a continuous rainfall during its first
three months, far exceeding any that had been experienced for sixty years.
Till then the average of the usual rainfall for four months had been 3
inches. In 1883 it had been 2.28 inches, and in 1884 it had been 4*89
inches; but in this year, 1885, it amounted in those three months to 19.27
inches, or 8J times what was expected! A veritable deluge!
The last of the heavy floods that consequently ensued lasted
for six days in April. It swept away several bridges and many miles of
temporary roads, caused numerous accidents, and did an infinity of mischief,
destroying camping-grounds, giving rise to malaria, and stopping the supply
of food.
Then after an interval of five weeks the floods again came
down, more severe than ever; the temporary bridges that had been erected
were swept away, and the line was cut in two; and this state of successive
catastrophes went on without cessation till the end of May. Then, however,
it stopped, and nothing so serious ever occurred again.
The Press occasionally showed its wisdom and knowledge, and
suggested that Browne might have foreseen these floods—“ The veriest tyro
would be expected to know of their annual occurrence! ” Obviously there are
floods and floods!
Some personal sketches of the work may now be conveniently
given, occasionally including some of Browne’s, but arranged chiefly with
regard to the order of the route.
“General Features.—A railway which starts at a level of about
500 feet above the sea, and rises to an elevation of 6,800 feet, must
necessarily present great difficulties in execution; besides, the features
of this inhospitable region are exceptionally formidable. Just beyond the
little village of Nari, a few miles from Sibi, the first of the great
difficulties on the line had to be encountered. Here three considerable
streams unite to form the Nari, and, although having but little water in
ordinary seasons, are torrents in time of flood, filling up the whole gorge
for some miles, and involving an immense quantity of heavy embankments,
tunnels, and cuttings. Yet for many months the work of the engineers halted,
as their half-complete embankments, with the staging and scaffolding of
their bridges, were washed away, and until the line could be completed
through this gorge, permanent way and other materials could not be carried
forward to the upper part of the line. This is one of the most weird tracts
through which a railway has ever been carried. The hills, absolutely bare,
rise above the valley for many thousands of feet in fantastic pinnacles and
cliffs. It is a scene of wildest desolation.
“At Kuchali also a very dangerous tunnel had to be made. So
many casualties occurred, owing to the tunnel falling in, that at last no
workmen could be got to enter it, except at a rate of wage fivefold that of
even the high rate prevailing on the line.
“The Chuppur Rift.—The Nari gorge traversed, the line ascends
along a mountain valley presenting no difficulties greater than are
ordinarily met with in mountain lines until the Chuppur Rift is reached, a
curious freak of nature whicn will certainly before long become a favourite
place of interest for Indian tourists. Here the great spurs of a rocky
mountain many hundred feet in height cross the drainage of the country and
present apparently a perfectly insuperable barrier. On close approach there
appears, however, a great rift transverse to the line of mountain, several
hundred feet high, and with just width enough for laden camels to pass along
the stony bed, through which the waters there, from what might have been an
extensive lake, now find their way. In dry seasons the bottom of the rift
presents merely the appearance of a very narrow rocky stream, difficult but
not impracticable for a horseman; but in floods a grand volume of water
rushes through with a depth of from 30 to 40 feet The character of the rock
forbids the idea of traversing it by means of a ledge, and the plan adopted
was that of two lines of continuous tunnels, one on each side of the rift,
ending at points opposite and on a level with each other, where they Ťare
connected and the rift is spanned by an iron girder bridge. To have
constructed these tunnels in the ordinary way from either end would have
involved a great expenditure of time owing to the extreme hardness of the
rock, and it was determined to effect the task by means of the combination
of a number of adits or approaches or short tunnels from the precipitous
sides of the rift, with the interior passages, ana it is in the construction
of these that the engineers and workmen were called on to display a degree
of physical courage as great as is ever needed in any operation of life. The
only way of making these adits or subsidiary tunnels was by letting down
workmen with ropes from the top of the cliff several hundred feet above the
point of operation. The first man down had to Sain a footing by driving a
crowbar into the perpenicular wall; after the first crowbar others were
driven in, and then a platform was erected from which blasting operations
could begin. So singular and difficult a piece of engineering has probably
seldom or never been accomplished before, and the name of the gallant
officer, Captain Buchanan Scott, who led the way in this perilous task,
deserves perpetual record in connection with the work. Six openings were
made on one side of the cliff for one tunnel and six on the other, and
galleries driven into them till points were reached from where the main
tunnel could be constructed right and left, so that the work could be
carried on by fourteen separate gangs; and in this way the whole tunnel was
blasted out in a few months.
“Louise Margaret Bridge.—The tunnel completed, there remained
the erection of the girder, and this is about 220 feet above the bed of the
gorge. The erection of it was not the least of the difficulties overcome by
the ingenuity and energy of General Browne and Captain Scott. This is the
bridge which was opened by H.R.H. the Duchess of Connaught, the first lady,
we believe, who ever visited the spot, and was named “ Louise Margaret ” in
her honour. The elevation of the Chuppur Rift is about 5,300 feet or one
mile above the sea; from thence the line rises with a ruling gradient of 1
in 45 till the summit level of 6,800 feet is jeached, first, however,
passing through another very difficult point known as Mud Gorge. Here the
difficulty is not rock, but a mountain mass which is little better than hard
mud, which had already made several bad slips carrying away the whole of the
line, and threatening more slips in the future. It will be some time before
the regime of Mud Gorge will be thoroughly established, and the line attain
a tone of durability.”
Another sketch runs thus:
“From the summit level of 6,800 feet the line descends to the
rocky pass or gorge of Garkhai, 5,700 feet, where it emerges on the elevated
tableland of Pesheen, and thence proceeds on a fairly level line to the foot
of the Khwaia Amran range, which separates Pesheen from Afghanistan. At
Bostan, twenty miles from Garkhai, a branch runs back to Quetta twenty
miles, and on the top of the Bolan Pass twenty-five miles farther on.”
A third sketch is as follows :
“The greater part of the country traversed is almost without
inhabitants, who do not grow enough food for their own consumption. For
miles ana miles there is no scene of vegetation, so that the whole of the
workmen had to be fed by supplies brought from a distance, and the feeding
of the large gangs, who averaged about 30,000 men on the works for many
months, had to be arranged for. The popular notion that malaria is due to
vegetation in tropical countries is dispelled on learning that these
desolate tracts, without a bush or blade of grass, have been the scene of
fever surpassing in virulence anything within ordinary Indian experience.
The whole line of the work is dotted with stones to mark the graves of the
unfortunate wretches whom the high wages offered have attracted from their
homes in India or Afghanistan. In one gang of 200 workmen the deaths from
fever for a long time were recorded at the average rate of ten per day. In
other words, the whole gang would have died out, if not renewed, in about
three months. It is almost needless to add that the European engineers have
had no immunity from illness; many have left with shattered constitution,
and those that remain are all more or less worn out by sickness, fatigue,
and climate."
Further remarks are not needed in regard to the construction
of the line, and we may therefore now revert to the subject of the
estimates, which have been already touched on.
On this subject “it would,” Browne had said, “be as
impossible for me to estimate what the Humai Railway would cost as it would
be for Lord Salisbury to estimate what it might cost England to go to war
with Russia.” Having examined the route and considered the nature of the
ground and localities involved, he had come with perfect justice and sound
wisdom to this conclusion and announced it boldly.
The subject is too technical to deal with fully in these
pages; but it may be said at once that, as in spite of all Browne’s
statements and their support by his professional superiors some of the very
high officials were not satisfied with the absence of any estimate on which
they could rely for guidance, an inquiry was instituted in 1886, and the
experts engaged made a report which, instead of censuring, led to
commendation, and to Browne being honoured with the K.C.S.I.
The worry and anxiety all this had entailed on Browne, when
already burdened with the tremendous difficulties of his task, cannot be
adequately described, and would probably have crushed any one else. To those
who were then cognisant of the state of matters it was a marvel that he
could bear up against it as he did.
But a few further remarks regarding the estimates so
persistently demanded, in spite of Browne’s statements and explanation, may
perhaps be usefully added. The estimates which he said he could not then
prepare are what are technically called detailed estimates, in which the
cost of each work or item is shown, arrived at by giving the dimensions and
then multiplying the quantities of work involved by the rates at which it is
assumed such work can be carried out. This is simple and straightforward
when the dimensions are certain and the rates well known or settled by
contract; but it is quite otherwise when, as in the present case, the sites
of the individual works, their details, their foundations, the character of
the rocks to be tunnelled, and all such data for guidance in the engineering
were entirely wanting at first and could become known only as the several
works progressed. In addition to this were
the repetitions of work that were made necessary by the
floods and similar causes. In such circumstances it does not require an
expert to realise that no estimates could be prepared on which reliance
could be placed. All that was possible was to send in “completion reports”
showing the actual cost of completed portions of work.
Browne’s case, it may be said, reminds one, as to the
inquisitor’s pressure put upon him, of Keats’s lines—
Half ignorant, he turns an easy wheel,
That sets sharp racks at work to pinch and feel.
The worry was continuous. Browne had submitted in December,
1884, an approximate estimate for 2611 lakhs, and urged that, with work
going on at high pressure, no more detailed estimates could be drawn much
before the actual completion of the line. The reply of the Government was,
“The prosecution of the railway is of the first importance. Consequently the
works must not be interfered with by the preparation of estimates” In spite
of this, the pressure from his immediate superior was maintained, while all
the time frequent commendations were bestowed by the Secretary of State and
the Government of India on General Browne and his staff for the rapid
progress made.
It was admitted that if war had broken out in 1887, the line
would have more than compensated for any excess of cost. Short staff for the
special non-engineering duties caused most of the difficulties complained
of—no local auditor, inadequate account office, staff for stores inadequate.
The conclusion of the report was, “ Great credit is due to the
Engineer-in-chief and his staff for the rapidity with which they have pushed
on the work, notwithstanding the difficulties of every description.” Such
was the judgment of the highest officials of the Government of India, who
thanked them for their able and comprehensive report.
Some further pertinent facts bearing on the undue departure
by the officials from the bona fide understanding on which Browne’s work was
being conducted may be now given. These are the outcome not of any
statements from Browne, but of the investigations of the most cognisant and
capable Engineer officials under the Government. The circumstances, if they
did not altogether account for such irregularities as had occurred, at any
rate very largely excused them. The extreme urgency of the case was
evidenced by the action of Government, and by its orders clearly
anticipating the immediate commencement of work. It was not surprising that
after reading the letters General Browne thought more of progress than of
estimates. If he set to work forthwith to align the road and start
operations, he would have no time for estimating. At first, too, Browne had
under him few but inexperienced officers, ignorant of the language, etc. In
April, 1884, the Secretary of State had telegraphed instructions for
pressing on the work, and the Government had replied so as to show that they
regarded it as of pressing necessity that the lower section of the road
should be completed in the next six months. In November, 1884, the Secretary
of State wired, “When will the line be completed?” to which the answer sent
(Browne’s) was, “ With money freely granted, in two and a half years ”—a
promise, it may be noted, redeemed by the fact that the engines ran over the
line in two years and six months.
As time progressed, the fame of these stupendous works
attracted the attention of tourists and others of eminence, who could speak
with weight, and the works were much visited in 1886. Browne’s old friend
and commander, Sir Donald Stewart, had seen and been much interested in
them, and had shown himself greatly pleased at the splendid health,
physique, and high spirits of the men, as well as their military smartness
and discipline. One of the visitors was the correspondent of a leading
London journal; and he, after five days of close inspection of the works,
commented on the contrast between what he had before heard and what he had
now seen of the line, especially of the Chuppur Rift, which “completely
exceeded his wildest imaginings of what human skill and energy could do.”
Another visitor was Lord Rosebery, who, besides examining and discussing the
railway, referred to frontier questions, about which his eyes (as he seemed
to admit) were opened in a way which he had not expected; and who also
appeared to be specially struck with the interest and enthusiasm of the
officers and men in the work—“Their soul seemed to be in it.” Just so!
During 1886 the sickness and difficulties that had been
troubling the work were not so mischievous as before, and it had now
progressed rapidly. Towards the end of the year it was hoped that the line
might be opened on February 14th following—Jubilee Day in India—but the
opening ceremony did not come off till March 27th, when the Chuppur Bridge
was finished, and an engine ran over the whole line from Sibi to Quetta.
A very distinguished company, including the Duke of Connaught
and Lord Roberts, were present to witness that ceremony, and it was
performed by H.R.H. the Duchess of Connaught, who named the bridge, and
after presiding over a very pleasant meeting desired Browne to address the
natives for her, and express her gratification with the great work—the
grandest in India.
The story which has now been told of the construction of the
Hurnai Railway has included such matters as the overwhelming floods, the
devastating epidemics and pestilence, and other material difficulties —some
of them "quite exceptional and unexpected— with which Browne had to contend;
and it will be recognised how severe a task it was to deal with them and how
great a feat to overcome them so successfully as he did But, in addition to
these, he was further oppressed by the official troubles, as explained. We
have now to deal only with the concluding episodes, which lay in the
clearing up of the misunderstandings that still existed in the mind of the
Viceroy, and with the authorities in England; all due primarily to the error
that still prevailed— respecting the exceptional arrangement on which the
enterprise had been started—having never been properly corrected.
The Viceroy, Lord Dufferin, had never seen the work, but had
been much troubled with the apparent muddle in its official management, and
it was primarily essential to disabuse him of any erroneous impressions he
may have formed. The work had been started before he entered on the
viceroyalty, and it was therefore possible that he was quite unaware of the
special features of the case—particularly those of its earlier days; he was,
moreover, deprived latterly of the sound guidance of Sir Donald Stewart, who
alone had a correct and thorough knowledge of the circumstances and
understandings on which the work had been started, but had left India, and
joined the Council in London, when Browne’s difficulties were becoming
serious.
Browne’s furlough had been sanctioned, but before taking
advantage of it he turned off immediately after the opening ceremony to
interview Lord Dufferin, whom he found in a very dissatisfied state of mind.
Learning that he had been very seriously misled as to the facts, Browne at
first caused much irritation by affirming this to be the case; but remaining
cool and firm, he was at length enabled to state specifically the initial
and crucial circumstances of which the Viceroy had evidently had no
knowledge whatever. Browne had carefully kept all demi-official letters, and
now produced those he had received telling him to adopt the very line of
action for which he had been latterly taken to task. This was a startling
revelation, and at once swept away the mistaken ideas that Lord Dufferin had
formed. With his eyes thus opened, having arrived at a true understanding of
the case, he corrected the tenour of his former communication to England,
and supported very warmly the representations Browne made to the home
authorities on reaching London.
Browne’s arrival in England was at a happy epoch —the first
jubilee of the Queen. He was heartily received at the India Office, and his
services and those of his staff were warmly acknowledged. He was now
a persona grata in high quarters, and received the K.C.S.I.
The Gazettes testified to the great self-sacrifice displayed,
the grave and disheartening difficulties successfully overcome under
circumstances which have seldom had a parallel, and tendered the thanks of
the Government to Browne and his staff.
During all 1888 he enjoyed his well-earned holiday —and had a
thorough rest, though not an idle -one. He was ever engaged on some subject
of public interest; and then, in 1889, he was selected by Lord Roberts for
the post of Quartermaster-General of the army in India—the first officer of
his corps who had ever been admitted into that very close borough, the army
staff at headquarters in its highest posts.
Lord Dufferin afterwards went over the line himself towards
the end of the year, having till then been prevented from doing so by other
engagements.
While engaged on his work, Browne, it may be remarked, in
continuation of what has been already said about his double, was being
constantly greeted as the Mukkur hajee, the old assumption being continued
by his Ghilzye admirers that it was not for them to comment on his having
become a Sahib. In fact, their original ideas had become more and more
strengthened and confirmed by the apparently permanent disappearance of the
real Mullah himself from Mukkur and that neighbourhood. |